Published on December 27, 2024
Pictured: Aerial image of project work site at El Dorado Park East
Long Beach Utilities began groundwater well construction on El Dorado 2 and Commission 23 A wells located in El Dorado Regional Park. The project will decommission the existing well and install new groundwater equipment to pump water out of the ground and convey it to the Long Beach Groundwater Treatment Plant.
The estimated project completion date is Spring 2027.
2024
Phase 1 - Drilling
Completed
2025
Phase 1 - Well Development
Ongoing
2026
Phase 2 - Well Development
Not Yet Started
2027
Phase 2 - Active Well
Phase 1: 7-Day Advanced Notification for 24-Hour Drilling Activity - August 26, 2024(PDF, 930KB)
For more information about the project, pleasecontact the Long Beach Utilities project manager at (562) 570-2334.